Waiting, waiting….
The house was (mostly) wrapped over two months ago, and since then, a little bit of internal electrical and plumbing fit out, but other than that, nothing. Every week we’re told the brickies will be here next week, but no show. The tight well fitting wrapping is degrading and starting to flap in the breeze.Continue reading “Waiting, waiting….”
Build Power Supply
We needed to provide power for the builders to save $10,000 on the contract price. We reckon we can provide it for around $500. (And that’s without installing our solar).

Second hand bricks & water supply for the builders
After a long wait, we love the second hand bricks. And resolved who was going to supply the water required for the mortar.